Macquarie Point Stadium cost estimate rises to $1.23 billion
The estimated cost of Hobart’s Macquarie Point Stadium has risen to $1.23 billion, with the Tasmanian Government also disclosing $315 million in precinct infrastructure and project delivery costs.
The stadium figure is $100 million above the previously published $1.13 billion estimate. Combined with $132 million for broader precinct infrastructure and $183 million in project delivery costs, the three disclosed categories total $1.545 billion.
The government released the figures today as negotiations continue with preferred builder BESIX Watpac, with a construction contract targeted for signing before Christmas.
The revised estimate remains subject to the final procurement process, which the government says could produce further changes to the cost.
The 23,000-seat Macquarie Point Stadium will feature a fixed roof over its oval playing field and spectator areas. It is intended to host AFL, cricket, concerts, conventions and other events, becoming the centrepiece of a wider redevelopment of Hobart’s waterfront.
Premier Jeremy Rockliff said the government remained committed to the project despite higher costs. The government attributes the increase to construction materials and labour prices, sustained high oil prices, the war in Iran and the complexity of the stadium and its parliamentary approval conditions.
The cost update also provides a clearer picture of expenditure beyond the stadium building. The $132 million precinct estimate includes a centralised car park, power and water upgrades and associated works. The $183 million delivery category covers costs managed by the Macquarie Point Development Corporation, including expenditure already incurred.
Questions remain about how the new figures compare with the previous budget. The government’s earlier $1.13 billion estimate included design, construction and commissioning, alongside project resourcing, consultant fees, contingencies and approximately $147.6 million in escalation allowances.

AAP reports that an additional contingency amount associated with the revised estimate has yet to be specified. The headline $100 million difference therefore provides only part of the picture, with the treatment of delivery costs and allowances also relevant to the overall change.
The government is seeking additional contributions from project partners and says any funding shortfall will be met through borrowing. It intends to recover borrowings through commercial opportunities across the precinct, with the development corporation preparing to take those opportunities to market during 2027.
The existing funding arrangements include a $240 million Australian Government contribution towards the stadium and precinct and $15 million from the AFL. Rockliff had previously committed to limiting Tasmania’s stadium contribution to $875 million, with the latest increase placing further pressure on that position.
BESIX Watpac was selected as preferred builder in October, entering exclusive negotiations with the development corporation. Agreeing the construction contract remains the next major delivery milestone, with preliminary works already underway on site.
The stadium is expected to be ready for the 2031 AFL season. The Tasmania Devils are scheduled to enter the competition in 2028, with delivery of the roofed venue forming a condition of the state’s AFL licence.
The surrounding Macquarie Point precinct is planned to incorporate public spaces, hospitality and commercial development, an Aboriginal culturally informed zone and housing at Regatta Point.
Rockliff said private investment would help realise the wider precinct’s potential, while Minister for Macquarie Point Urban Renewal Eric Abetz said the stadium would support year-round events and visitation.
Latest News
Olympics · 27 Nov 2026Melbourne’s Olympic venues leave a lasting legacy 70 years on
AFL · 26 Nov 2026Builder to examine future expansion of Macquarie Point Stadium
Concerts · 26 Nov 2026Surfers Music Hall unveiled as Gold Coast’s new 2,500-capacity venue
Sponsorship · 25 Nov 2026Adelaide Entertainment Centre to become RAA Entertainment Centre