Commencing in May 2006, the Sydney Cricket Ground Trust will
undertake three major capital works projects to upgrade the facilities at
Aussie Stadium. At a cost of nearly $7M, these projects are designed to
enhance the spectator experience and bring you even closer to the action.
Project One: INCREASE IN SEATING
CAPACITY - $4.2M
Aussie Stadium's capacity is set to increase to 45,500 with
3,000 additional seats to be installed in two main stages of construction.
STAGE ONE - UPPER DECKS
Construction: May 2006 to September 2006
The first stage will see the upper decks of the Nick
Shehadie Stand (Eastern) and the Western Stand extended by two rows towards
the field, adding an additional 900 seats to the top level. This will add an
additional 450 seats to the Members Reserve.
PDF - Upper deck aerial view
PDF - Upper deck - seating
Click here: Upper Deck Construction photos
STAGE TWO - LOWER SEATING BOWL
Construction: May 2006 to February 2007
The second stage will see the lower seating bowl at
concourse level increased by 2100 seats.
The eastern and western concourses will increase by three
rows in the middle, decreasing to one row towards the corners of the field.
An additional five rows will be added to the northern and
southern ends closer to the sidelines.
These developments will bring you closer to the action, and
will further enhance Aussie Stadium's highly acclaimed match-day atmosphere.
PDF - Lower Seating Bowl - aerial view
PDF - Lower Seating Bowl - additional seating
PDF - Lower Seating - scoreboard addition
Click here: Northern & Southern end construction photos
The escalation in atmosphere will prove to be a
tremendous asset for the NSW Waratahs, Sydney FC, Sydney Roosters, the
Australian Kangaroos Rugby League team, and the Socceroos when they play at
Aussie Stadium.
Project Two: FOOD & BEVERAGE
OUTLETS - $1.75M
FOOD & BEVERAGE OUTLETS
Completion: December 2006
Two additional food outlets and one bar outlet will be
constructed on the eastern public concourse of Aussie Stadium.
ADDITIONAL TOILETS
Completion: December 2006
Additional female toilets will be constructed on the eastern
public concourse of Aussie Stadium.
Project Three: VIDEO SCREEN - $1M
Construction: May 2006 to September 2006
A second videoscreen will be installed at Aussie Stadium.
Measuring 9.6m x 5.4m, the widescreen LED video screen will be positioned at
the southern end.
For further details,
click here. |